ALBARIVAS Wind Farm

On December 1st, 2013, the substation for the Alba Rivas Wind Farm in Nicaragua was successfully energized. TSK has developed the BOP of the wind farm, the 230 KV substation, consisting of a two position line with 230 KV, one position transformer of 230/34.5kV and an output of 50 MWA. The overall production capacity is 44 MVA, with a total of 22 V100 machines manufactured by Vestas.

This farm is the second TSK carries out in the surroundings of Lake Managua. The two farms have a total power capacity of 100 MW, which contributes to the development of the electrical system of Nicaragua.